May 8, 2013 - Project update:
Much technical work has been going on behind the scenes since the commencement of this project in January. At this time, the new hosted environments have been built and we’ve almost completed our first round of end-user testing. Testing has been underway for nearly two weeks and we recognize all of the effort that has been put forth by staff in the administrative offices that will make the final stage of this important University project successful.
We are excited to have hit this milestone in our project plan and look forward to the next round of testing, which will begin in mid-May. We greatly appreciate both the dedication of the participants as well as the patience of the community which collectively will ensure the timely completion of the project and a smooth transition into our hosted environment on July 5th.
University Strategic Goals and Objectives
Objectives
- Wilkes' reliance on Banner for its business and administrative processes requires reliable 24/7 system availability
- Wilkes' webssite presence is an essential communication tool for the campus community and requires reliable 24/7 availability and access
Goals
- Identify a solution that provides cost-effective high availability, reliable business continuity leveraging technologies to achieve 24/7 availability form any internet connected computer.
- For more information on the solution chosen to meet those needs visit the link below or view the video provided.
Project Objectives and Scope
Objectives
- Transition mission critical administrative and communications systems currently managed from the campus Data Center to a secure, remote facility designed specifically to provide optimal environmental and redundancy conditions and protections from natural disasters or other events that would otherwise impact system access and availability
Scope
- Banner Systems (Student, Financial Aid, Finance, HR)
- Cognos/ODS/EDW
- WIlkes.edu website
- Wilkes Active Directory Domain (read-only)
Milestones
Task
|
Target
Completions
|
|
Complete planning and assessment of Wilkes Environment
|
January - February |
|
Standup of new hosted environments
- Infrastructure/Networking/Access/AMs
- OS/Apps/DB
- Pre-install verification/validation
- Post install verifications/validation
|
February - March |
|
Verify/Validate Banner & 3rd Party integrations/interfaces
- Tuesday April 23 - Monday May 6 (10 Days)
- Wednesday May 15 - Friday May 24 (8 days)
- Tuesday June 11 - Friday June 14 (4 days)
|
April - June |
|
Load Testing of hosted environment
|
May - June |
|
Code freeze of environment (minimum 30 days prior to Go-Live)
|
May 1 |
|
Hosting Go/No-Go deicsion for Production Cutover determined by Wilkes University
|
June 21 |
|
Hosting Go-Live
- Verify/Validate Banner and 3rd party integrations/interfaces
|
July 4th weekend |
|
Transition to steady-state operational support
|